Progressing, although really slow. Having huge problems getting the windows from Andersen.
Supply chain issues are slowing everyone down. 15 weeks for cabinets. 16 weeks for windows. Plywood unavailable. Cost of house wrap has more than doubled. Some items are just outright unavailable. 4 months for electric service connections. Design #4 is nearing completion. Below is a progress preview of the design. |